November 2008 - April 2009
|
|
Earth work of remaining roads in Sector ‘C’ and ‘D’ in progress. Subbase material being brought at site. Drains along road M-3 and M-4 are in progress for rainwater drainage. |
| |
|
|
Footpath with Tuff tiles has been completed on the rightside and the one on left-side on Major Road M-1 is in progress. |
|
|
|
24” diameter Rcc pipe drain laid in the median of major road M-1 in about 1300 Rft length for storm water drainage. |
| |
|
|
Sanitary sewers have been laid along major roads M-3 & M-10 and work of laying Sewers is in progress along major road M-6. |
| |
|
|
Crosses for water supply and sewerage system have been laid on Avenue I & II and a few streets of Sector ‘C’. |
| |
|
|
Work on open drains along road M-3 has been completed and M-4 drain is in progress. |
|
|
|
|
|
|
April - October 2008
|
|
Earthwork of roads in progress. Superstructure of roads like Sub-base/Base course being laid and compacted in sector 'B' and 'C'. Asphalt concrete/carpeting laid on major road M-1, Avenue 1 and Street No 1 to 5 of Sector 'B'. Footpaths along major road M-1 are in progress. |
| |
|
|
Box culverts on roads M-1, Avenue I and II have been completed and the one on road M-4 has been taken up for drainage of rain water. Open drains along road M-3 and M-4 are also in progress. |
|
|
|
Sanitary Sewerage System has been laid along roads M-1, Avenue I and II and Street No. 1 to 8 of Sector 'B'. |
| |
|
|
Crosses for water supply have been laid in Sector 'B' and water lines shall be laid in the frontal area shortly. |
| |
|
|
Street light poles have been brought at site and some have been installed/fixed on major road M-1. |
| |
|
|
Plantation and turfing has been done in the median of major road M-1. |
|
|
|
|
|
|
Jan - March 2008
|
|
Graceland Housing feels great pleasure in announcing the issuance of Full and Final NOC from Ministry of Defence. This by no standards is a small achievement. In this connection MOD Letter No.6/17/Misc/D-28/2005 dated 11th March 2008 may be cited for reference. |
| |
|
|
Work is in full progress and the project is coming up exactly as it was conceived on the standards of DHA phase II Islamabad. Work on Main Boulevard is in full swing. The culverts on Main Boulevard and on Avenue I and II for drainage of rain water is nearing completion. |
|
|
|
Work is also in progress on water supply pipelines and sewerage system manholes in the frontal area. |
|
|
| |
|
Oct 2007 - December 2007
|
|
The heavy monsoon rains caused lot of damage to the earth work of roads done earlier in the scheme; there were deep rain cuts and ravines. |
|
|
|
Repair and restoration work is in progress but the recent winter rains and severe cold weather conditions intermittently obstructed that over the last more than one month now. |
|
|
|
Beside restoration works, other original development works like construction of Box-Culvert on Major road M-1 has been completed and work on Box-Culverts on Avenues and construction of drains for the disposal of rainwater is in progress. |
| |
|
|
Pipe drains in the Central median of major road M-1 is in progress alongwith rainwater chambers, catch pits and gratings. |
|
|
|
|
July 2007 - September 2007
|
|
The progress of development work was at its lowest ebb during this period due to heavy monsoon rains in the area. However, with our concerted efforts N.O.C was obtained from Environmental Protection Department, Lahore Government of Punjab after fulfilling all their requirements and meeting their concerns regarding the usual environmental issues involved in the development of housing scheme like assuring safe piped water supply and Sewage Treatment Plant besides the proper Solid Waste Management and its disposal. |
|
|
|
|
April 2007 -June 2007
|
|
Cutting and filling of earth for roads in streets of:
- Sector D: Street No. 3, 4, 5, 6, 7, 8, 9,10 and 15.
- Sector E: Street No.3 and 4.
|
|
|
|
The Graceland Housing Scheme was declared clear of the ‘Negative Area’ by the Ministry of Defence Government of Pakistan and a Gazette Notification was issued to this effect in April 2007. |
|
|
|
|
Oct 2006 - Mar 2007
|
|
Cutting and Filling of Earth for Roads in Streets of:
- Sector B: street No 2,3, 4, 5, 6 and 7 i.e all streets of Sector B.
- Sector C: Street No 2 and Park Road.
- Major Roads: M-3, M-6, M-7, M-8, M-11 and Central Square / Markaz.
|
|
|
|
Filling of Earth in Depressions for Preparing Sub Grade of Roads of:
- Sector A: Second Avenue.
- Sector C: Park Road , First Avenue and Street No. 8.
- Sector D: Street No. 7, 9, 10, 11, 12 and 14.
- Major Roads: M1, M3, M4, M6, M7, M8, Central square / Markaz.
|
|
|
|
|
|
Jul - Sep 2006
|
|
|
|
Apr - Jun 2006
|
|
|
|
Jan - Mar 2006
|
|
|
|
Oct - Dec 2005
|
|
|
|
July - Sep 2005
|
|
Topographic Survey of land of Graceland Housing Scheme . |
|
|
|
Preparation of Contour Plan and initial Town Planning. |
|
|
|
Preparation of Zoning Plan and Master Plan of the Housing Scheme. |
|
|
Approval of the Master Layout Plan of the Scheme. |
|
|
Infrastructure design work and its approval by the client. |
|
|
|
|
|
|
|
|